From: Resource-loaded piping spool fabrication scheduling: material-supply-driven optimization
Activity ID | Activity name | Labor | Duration (min) |
---|---|---|---|
(a). fabrication activities for Spool 1 | |||
 A1 | Fit 2″ elbow and 2″ flange | 2 Fitters | 30 |
 B1 | Weld 2″ elbow and 2″ flange (sub1_1) | 1 Welder | 30 |
 C1 | Fit the sub1_1 with 2″ pipe | 2 Fitters | 11 |
 D1 | Weld the subassembly with 2″ pipe (sub1_2) | 1 Welder | 30 |
 E1 | Fit sub1_2 with olet | 2 Fitters | 13 |
 F1 | Weld sub1_2 with olet (sub1_3) | 1 Welder | 17 |
 G1 | Fit two 6″ pipes together | 2 Fitters | 36 |
 H1 | Weld two 6″ pipes together (sub1_4) | 1 Welder | 44 |
 I1 | Fit sub1_3 and sub1_ 4 | 2 Fitters | 24 |
 J1 | Weld sub1_3 and sub1_4 | 1 Welder | 57 |
(b). fabrication activities for Spool 2 | |||
 A2 | Fit 6″ elbow with 6″ pipe | 2 Fitters | 41 |
 B2 | Weld 6″ elbow with 6″ pipe (sub2_1) | 1 Welder | 68 |
 C2 | Fit sub2_1 with 6″ pipe | 2 Fitters | 39 |
 D2 | Weld sub2_1 with 6″ pipe | 1 Welder | 69 |
(c). fabrication activities for Spool 3 | |||
 A3 | Fit 6″ hydro pipe and 6″ elbow | 2 Fitters | 12 |
 B3 | Weld 6″ hydro pipe and 6″ elbow (sub3_1) | 1 Welder | 42 |
 C3 | Fit 6″ elbow and 6″ pipe | 2 Fitters | 15 |
 D3 | Weld 6″ elbow and 6″ pipe (sub3_2) | 1 Welder | 14 |
 E3 | Fit sub3_1 and sub3_2 | 2 Fitters | 18 |
 F3 | Weld sub3_1 and sub3_2 (sub3_3) | 1 Welder | 12 |
 G3 | Fit 6″ pipe and tee | 2 Fitters | 31 |
 H3 | Weld 6″ pipe and tee (sub3_4) | 1 Welder | 56 |
 I3 | Fit sub3_4 and reducer | 2 Fitters | 37 |
 J3 | Weld sub3_4 and reducer (sub3_5) | 1 Welder | 46 |
 K3 | Fit sub3_5 and 3″ pipe | 2 Fitters | 19 |
 L3 | Weld sub3_5 and 3″ pipe (sub3_6) | 1 Welder | 15 |
 M3 | Fit sub3_6 and 3″ Flange | 2 Fitters | 11 |
 N3 | Weld sub3_6 and 3″ Flange (sub3_7) | 1 Welder | 130 |
 O3 | Fit sub3_3 and 6″ pipe | 2 Fitters | 27 |
 P3 | Weld sub3_3 and 6″ pipe (sub3_8) | 1 Welder | 52 |
 Q3 | Fit sub3_7 and sub3_8 | 2 Fitters | 29 |
 R3 | Weld sub3_7 and sub3_8 | 1 Welder | 80 |