Table 2 ANOVA results showing correlation between the factor;delay experienced in dealing with the budget querywith a number of dependent variables namely;the frequency of problematic issues during the remote construction project’s period, (level of significance <0.05)

From: The potentials of and barriers to the utilization of advanced computer systems in remote construction projects: case of the Kingdom of Saudi Arabia

Dependent variable: the frequency of problematic issues during the remote construction project’s period (i.e. from start to completion

Independent variable (factor): the delay experienced in dealing with the budget query

Sum of Squares

df

Mean Square

F

Sig.

Mistakes in construction works

Between Groups

6.105

4

1.526

2.758

0.043

Within Groups

18.818

34

0.553

 

Shortage in site equipment

Between Groups

15.838

4

3.959

3.934

0.01

Within Groups

33.215

33

1.007

 

Delay in the conduction of field survey by the contractor

Between Groups

15.123

4

3.781

5.469

0.002

Within Groups

22.121

32

0.691

 

Unavailability of the supervision engineers during sample testing stages

Between Groups

19.735

4

4.934

5.869

0.001

Within Groups

27.739

33

0.841

 

Improper construction methods implemented by the contractor

Between Groups

5.554

4

1.388

3.325

0.022

Within Groups

13.365

32

0.418

 

Inadequate equipment used

Between Groups

10.849

4

2.712

4.082

0.008

Within Groups

22.587

34

0.664

Â