Dependent variable: the frequency of problematic issues during the remote construction project’s period (i.e. from start to completion | Independent variable (factor): the delay experienced in dealing with the budget query | |||||
---|---|---|---|---|---|---|
Sum of Squares | df | Mean Square | F | Sig. | ||
Mistakes in construction works | Between Groups | 6.105 | 4 | 1.526 | 2.758 | 0.043 |
Within Groups | 18.818 | 34 | 0.553 | Â | ||
Shortage in site equipment | Between Groups | 15.838 | 4 | 3.959 | 3.934 | 0.01 |
Within Groups | 33.215 | 33 | 1.007 | Â | ||
Delay in the conduction of field survey by the contractor | Between Groups | 15.123 | 4 | 3.781 | 5.469 | 0.002 |
Within Groups | 22.121 | 32 | 0.691 | Â | ||
Unavailability of the supervision engineers during sample testing stages | Between Groups | 19.735 | 4 | 4.934 | 5.869 | 0.001 |
Within Groups | 27.739 | 33 | 0.841 | Â | ||
Improper construction methods implemented by the contractor | Between Groups | 5.554 | 4 | 1.388 | 3.325 | 0.022 |
Within Groups | 13.365 | 32 | 0.418 | Â | ||
Inadequate equipment used | Between Groups | 10.849 | 4 | 2.712 | 4.082 | 0.008 |
Within Groups | 22.587 | 34 | 0.664 | Â |