Type of the remote construction site’s query | Mean | Std. deviation | Skewness |
---|---|---|---|
Reporting QA/QC problems | 4.13 | 0.992 | -0.825 |
Contract drawings | 4.11 | 0.841 | -0.468 |
Reporting the site inspection outcomes | 4.06 | 0.942 | -0.62 |
Clarification of Design information | 4.02 | 0.944 | -1.016 |
Accident reporting | 3.96 | 1.083 | -0.879 |
Violations reporting | 3.94 | 1.131 | -1.001 |
Progress reporting | 3.91 | 1.08 | -1.014 |
Revisions to submittals | 3.89 | 0.983 | -0.209 |
Initiate site inspections | 3.89 | 1.005 | -0.45 |
Contract specifications | 3.83 | 1.018 | -0.693 |
Updated Schedule | 3.83 | 1.253 | -0.72 |
Sample test results | 3.77 | 1.165 | -0.812 |
Exception reporting | 3.74 | 1.206 | -0.879 |
Meeting minutes | 3.68 | 1.163 | -0.72 |
As-built records | 3.64 | 1.293 | -0.73 |
Delay records | 3.63 | 1.388 | -0.752 |
Subcontractor work’s progress information | 3.48 | 1.11 | -0.452 |
Products Catalog | 3.36 | 1.342 | -0.368 |
Budget | 3.33 | 1.266 | -0.242 |
Material cost accounting | 3.26 | 1.307 | -0.447 |
Equipment cost accounting | 3.2 | 1.222 | -0.316 |
Visitor’s log | 3.13 | 1.377 | -0.135 |