Table 3 How fast the ACMS would accelerate the feedback of the remote construction site’ queries,(Mean value scale: 1 = do not accelerate to 5 = highly accelerate)

From: The potentials of and barriers to the utilization of advanced computer systems in remote construction projects: case of the Kingdom of Saudi Arabia

Type of the remote construction site’s query

Mean

Std. deviation

Skewness

Reporting QA/QC problems

4.13

0.992

-0.825

Contract drawings

4.11

0.841

-0.468

Reporting the site inspection outcomes

4.06

0.942

-0.62

Clarification of Design information

4.02

0.944

-1.016

Accident reporting

3.96

1.083

-0.879

Violations reporting

3.94

1.131

-1.001

Progress reporting

3.91

1.08

-1.014

Revisions to submittals

3.89

0.983

-0.209

Initiate site inspections

3.89

1.005

-0.45

Contract specifications

3.83

1.018

-0.693

Updated Schedule

3.83

1.253

-0.72

Sample test results

3.77

1.165

-0.812

Exception reporting

3.74

1.206

-0.879

Meeting minutes

3.68

1.163

-0.72

As-built records

3.64

1.293

-0.73

Delay records

3.63

1.388

-0.752

Subcontractor work’s progress information

3.48

1.11

-0.452

Products Catalog

3.36

1.342

-0.368

Budget

3.33

1.266

-0.242

Material cost accounting

3.26

1.307

-0.447

Equipment cost accounting

3.2

1.222

-0.316

Visitor’s log

3.13

1.377

-0.135