Table 4 Simulation experiments for schedule adaption on day 40

From: Reactive scheduling based on actual logistics data by applying simulation-based optimization

 

Exp3

Exp4

Infeasible Target Schedule

Remaining duration in days

161

158

152

Costs (fix) in $

96,600

94,800

 

Costs (labor) in $

104,220

104,172

106,752

Costs (crane) in $

167,184

167,184

167,184

Costs (shift extension) in $

0

18,480

0

Costs (crane extension) in $

13,000

4,200

0

Total costs in $

381,004

388,836

365,136