Table 4 Simulation experiments for schedule adaption on day 40

From: Reactive scheduling based on actual logistics data by applying simulation-based optimization

  Exp3 Exp4 Infeasible Target Schedule
Remaining duration in days 161 158 152
Costs (fix) in $ 96,600 94,800  
Costs (labor) in $ 104,220 104,172 106,752
Costs (crane) in $ 167,184 167,184 167,184
Costs (shift extension) in $ 0 18,480 0
Costs (crane extension) in $ 13,000 4,200 0
Total costs in $ 381,004 388,836 365,136