Table 2 Required materials for fabricating the three sample spools

From: Resource-loaded piping spool fabrication scheduling: material-supply-driven optimization

Material name Quantity
6″, Sch.40 Pipe 23 meter
2″, Sch.80 Pipe 1 meter
3″, Sch.40 Pipe 1.3 meter
2″, Sch.80 Elbow 1
6″, Sch.40 Elbow 4
2″, Sch.80 Flange 1
3″, Sch.40 Flange 1
2″ × 6″, Sch.80/Sch.40 Olet 1
6″ Hydro pipe 1
6″ × 3″, Sch.40 Reducer 1
6″, Sch.40 Tee 1