Table 4 Materials for fabricating the three sample spools

From: Resource-loaded piping spool fabrication scheduling: material-supply-driven optimization

Activity ID

Activity name

Required material

Name

Quantity

A1

Fit 2″ elbow and 2″ flange

2″ elbow

1

2″ Flange

1

C1

Fit the sub1_1 with 2″ pipe

2″ pipe

1 meter

E1

Fit sub1_2 with olet

Olet

1

G1

Fit two 6″ pipes together

6″ pipe

12.1meter

A2

Fit 6″ elbow with 6″ pipe

6″ elbow

2

6″ pipe

0.6 meter

C2

Fit sub2_1 with 6″ pipe

6″ pipe

5.8 meter

A3

Fit 6″ hydro pipe and 6″ elbow

6″ hydro pipe

1

6″ elbow

1

C3

Fit 6″ elbow and 6″ pipe

6″ elbow

1

6″ pipe

0.6 meter

G3

Fit 6″ pipe and tee

6″ pipe

2.7 meter

Tee

1

I3

Fit sub3_4 and reducer

6″ × 3″ reducer

1

K3

Fit sub3_5 and 3″ pipe

3″ pipe

1.3 meter

M3

Fit sub3_6 and 3″ Flange

3″ Flange

1

O3

Fit sub3_3 and 6″ pipe

6″ pipe

0.6 meter