Table 1 Experimental margin of error for each correlation level

From: Impact of linear correlation on construction project performance using stochastic linear scheduling

Correlation Level (k) 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
Error - Crew Idle Time % 3.74 3.69 3.81 3.82 3.73 3.80 3.75 3.76 3.92 3.64 3.06
Error - Missed Opportunities % 3.76 3.62 3.73 3.65 3.58 3.74 3.67 3.47 3.32 3.45 3.73