From: Deconstruction waste management through 3d reconstruction and bim: a case study
<Wall material takeoff> | |||||
---|---|---|---|---|---|
A | B | C | D | E | F |
Material: name | Type | Phase demolis | Material: volume | Unit cost ($/m3) | Cost ($) |
Asbestos | |||||
Asbestos | Hazardous materials | Phase 3 | 0.42Â m3 | 300 | 124.874983 |
Asbestos: 26 Brick, common | Â | Â | 0.42Â m3 | Â | 124.874983 |
Brick, common | Â | Phase 7 | 508.92Â m3 | 300 | 152,675.861538 |
Brick, common: 60 Concrete masonry Units | Â | Â | 508.92Â m3 | Â | 152,675.861538 |
Concrete masonry units | Atrium wall 100 | Phase 7 | 10.06Â m3 | 300 | 3019.045148 |
Concrete masonry units | UTS-exterior-wall-240 | Phase 10 | 180.48Â m3 | 300 | 54,142.794872 |
Concrete masonry units: 69 Gypsum wall board | Â | Â | 190.54Â m3 | Â | 57,161.84002 |
Gypsum wall board | UTS-exterior-wall-240 | Phase 10 | 18.05Â m3 | 300 | 5414.279487 |
Gypsum wall board: 57 | Â | Â | 18.05Â m3 | Â | 5414.279487 |
Grand total: 312 | Â | Â | 717.92Â m3 | Â | 215,376.856029 |